Gas & steam power stations

Combined power station, Aghada, Ireland (430 MW)

New plant

Aghada

  • Appointment of lead engineers for electrical- and control engineering
  • Steady-state study
  • 220 kV network connection to EirGrid
  • Entire planning of auxiliaries system
  • Drafting specifications for component procurement
  • Load-flow / short-circuit calculations and selectivity analysis
  • Overvoltage protection and insulation coordination
  • Document management
  • Interface management to sub-contractors
  • Planning of medium- and low-voltage switchgear
  • Design of DC/UPS, emergency power generator and transformers
  • Grounding / potential equalization and lightning protection
  • Cable routing
  • Electrical arrangement design
  • Building-technology engineering – lighting, grounding and lightning protection